# DFW Kiln Permitting
Air rules make a new lime kiln near Dallas-Fort Worth very hard to build. This protects USLM, and it also limits USLM.
## The rule
- DFW is a severe nonattainment zone for the 2008 federal ozone standard.
- A new kiln needs a New Source Review permit from the Texas Commission on Environmental Quality (TCEQ).
- The permit needs three things: proof of no worse air quality, bought emissions offsets, and Best Available Control Technology.
- The source says no new DFW lime kiln has been permitted in decades. It also says USLM's Cleburne kilns run on grandfathered permits.^[Colubeat Investment Desk, 28 May 2026, https://colubeatid.substack.com/p/united-states-lime-and-minerals-inc]
> [!warning] Verify
> Johnson County (Cleburne) is in the DFW ozone area. Check the "grandfathered" claim against TCEQ permit records. A grandfathered permit can be reopened.
## A new entrant needs all of these
```mermaid
graph LR
A[Find pure limestone<br/>near DFW] --> B[Buy thousands of acres<br/>in a growing county]
B --> C[Win NSR permit,<br/>buy offsets]
C --> D[Build kiln<br/>~$65M+]
D --> E[First ton,<br/>years later]
```
- Each step can fail. Together they make entry unlikely inside a five-year view.
## It cuts both ways
- USLM's own new kiln had to pass TCEQ.
- A third or fourth Cleburne kiln (2028–2030) may not pass.
- Then growth must come from Arkansas, Oklahoma or a new site outside DFW.
- Those sites sell a lower-margin product mix. Growth there earns less per ton. See [[Texas Lime Concentration Risk]].
> [!important] The moat caps the growth
> The permit wall keeps rivals out. It also keeps USLM's best plant near its present size.
----